The characteristics of Thermal Power Plants | OJSC "Dniproenergo | OJSC Donbasenergo | OJSC Zakhidenergo | OJSC Centrenergo | | Prydniprovska TPP | Starobeshivska TPP | Burshtynska TPP | Trypilska TPP | | Kryvorizka TPP | Slovianska TPP | Dobrotvirska TPP | Zmiivska TPP | | Zaporizka TPP | | Ladyzhinska TPP | Vuglegirska TPP |
Prydniprovska TPP Installed capacity - 1765 MW Number of power units 8 Basic designed fuel: For power units with an installed capacity of 150 MW - coal of the АШ grade (caloric value 6010 kcal/kg); For power units with an installed capacity of 285-310 MW - coal of the АШ grade (caloric value 5900 kcal/kg); The share of consumption of natural gas in the fuel structure in 2007 13.4% | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007)g/kW*h | | 7 | 150 | 1959 | 297745 | operating | 411,5 | | 8 | 150 | 1960 | 303023 | operating | | 9 | 150 | 1960 | 302806 | operating | | 10 | 150 | 1961 | 289785 | operating | | 11* | 310 | 1963 | 229084 | operating | | 12 | 285 | 1964 | 221579 | laying-up | | 13 | 285 | 1965 | 274924 | operating | | 14 | 285 | 1966 | 246384 | laying-up | *The turbine (310 MW) was changed in 2001.
Kryvorizka TPP Installed capacity - 2820 MW Number of power units-10 Basic designed fuel: coal of the "T" grade (caloric value 6550 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 6.4 % | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 282 | 1965 | 269562 | operating | 383,5 | | 2 | 282 | 1966 | 268133 | operating | | 3 | 282 | 1966 | 252773 | reconstruction | | 4 | 282 | 1968 | 206237 | operating | | 5 | 282 | 1968 | 252179 | operating | | 6 | 282 | 1969 | 229469 | operating | | 7 | 282 | 1970 | 190390 | laying-up | | 8 | 282 | 1970 | 231572 | operating | | 9 | 282 | 1972 | 178750 | laying-up | | 10 | 282 | 1973 | 172063 | laying-up |
Zaporizka TPP Installed capacity - 3600 MW; Number of power units - 7; Basic designed fuel: For power units with an installed capacity of 300 MW - coal of the ГСШ grade (caloric value 5000 kcal/kg); For power units with an installed capacity of 800 MW - gas; The share of consumption of natural gas in the fuel structure in 2007 for power units with an installed capacity of 300 MW -5.6%;
| № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 300 | 1972 | 235837 | operating | 358,6 | | 2 | 300 | 1972 | 233023 | operating | | 3 | 300 | 1972 | 229340 | operating | | 4 | 300 | 1973 | 210611 | operating | | 5 | 800 | 1975 | 148343 | operating | | 6 | 800 | 1976 | 127365 | laying-up | | 7 | 800 | 1977 | 133159 | operating | Starobeshivska TPP Installed capacity - 1725 MW; Number of power units - 10; Basic designed fuel: coal of the АШ grade (caloric value 6010 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 8.24%
| № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 4 | 175 | 1961 | 233264 | reconstruction | 421,0 | | 5 | 175 | 1962 | 272208 | operating | | 6 | 175 | 1962 | 265368 | operating | | 7 | 175 | 1963 | 256415 | reconstruction | | 8 | 175 | 1963 | 265772 | operating | | 9 | 175 | 1964 | 254859 | operating | | 10 | 175 | 1965 | 266719 | operating | | 11 | 175 | 1965 | 255830 | operating | | 12 | 200 | 1966 | 258774 | operating | | 13 | 175 | 1967 | 236233 | operating | Slovianska TPP Installed capacity - 800 MW; Number of power units -1; Basic designed fuel: coal of the АШ grade (caloric value 5600 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 4.05% | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 7 | 800 | 1971 | 235548 | operating | 410,9 | Burshtynska TPP Installed capacity - 2300 MW; Number of power units -12; Basic designed fuel: coal of the Г grade (caloric value 5000 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 5.9% | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008,hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 195 | 1965 | 248451 | operating | 413,9 | | 2 | 185 | 1965 | 241386 | operating | | 3 | 185 | 1966 | 248665 | operating | | 4 | 195 | 1966 | 260270 | operating | | 5 | 195 | 1967 | 265324 | operating | | 6 | 185 | 1967 | 255693 | operating | | 7 | 185 | 1968 | 263708 | reconstruction | | 8 | 195 | 1968 | 259396 | operating | | 9 | 195 | 1968 | 238799 | operating | | 10 | 195 | 1969 | 248064 | operating | | 11 | 195 | 1969 | 216092 | operating | | 12 | 195 | 1969 | 209642 | operating | Dobrotvirska TPP Installed capacity - 600 MW; Number of power units - 2; Basic designed fuel: coal of the Г grade (caloric value 4950 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 2.8%
First line | № of boiler, turbine | Type of boiler, turbine | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | | Boiler 4 | TP-10 | 1959 | 188877 | laying-up | | Boiler 5 | ТP-10 | 1959 | 270309 | operating | | Boiler 6 | ТP-10 | 1959 | 278723 | operating | | Boiler 7 | ТP-10 | 1960 | 287322 | operating | | Boiler8 | ТP-10 | 1961 | 275156 | operating | | Boiler 9 | ТP-10 | 1961 | 271908 | operating | | Boiler 10 | ТP-10 | 1962 | 264159 | operating | | Turbine 4 | ВК-100-6 | 1960 | 328802 | reconstruction | | Turbine 5 | ВК-100-6 | 1960 | 298122 | operating | | Turbine 6 | ВК-100-6 | 1961 | 293003 | operating | Second line | № of boiler, turbine | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | Boiler 7 | 150 | 1963 | 297906 | operating | 425,3 | | Boiler 8 | 150 | 1964 | 278588 | operating | Ladyzhinska TPP Installed capacity - 1800 MW; Number of power units - 6; Basic designed fuel: coal of the ГСШ grade (caloric value 5000 kcal/kg) The share of consumption of natural gas in the fuel structure in 2007 1.0% | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 300 | 1970 | 212513 | operating | 378,6 | | 2 | 300 | 1971 | 205471 | operating | | 3 | 300 | 1971 | 197629 | operating | | 4 | 300 | 1971 | 208854 | operating | | 5 | 300 | 1971 | 197153 | operating | | 6 | 300 | 1971 | 207852 | operating | Trypilska TPP Installed capacity - 1800 MW; Number of power units - 6; Basic designed fuel: For power units 1-4 - coal of the АШ grade (caloric value 5790 kcal/kg); For power units 5-6 - gas; The share of consumption of natural gas in the fuel structure in 2007 10.95% | № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 300 | 1969 | 247373 | operating | 406,9 | | 2 | 300 | 1970 | 256142 | operating | | 3 | 300 | 1970 | 251918 | operating | | 4 | 300 | 1970 | 242976 | operating | | 5 | 300 | 1971 | 175939 | operating | | 6 | 300 | 1972 | 171531 | operating | Zmiivska TPP Installed capacity - 2175 MW; Number of power units -10; Basic designed fuel: For power units with an installed capacity of 175 MW - coal of the АШ grade (caloric value 6010 kcal/kg); For power units with an installed capacity of 275-300 MW - coal of the Т grade (caloric value 6150 kcal/kg); The share of consumption of natural gas in the fuel structure in 2007 8.3%
| № of the power unit | Capacity, MW | The year of putting into operation | Operating time by 01.01.2008, hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 175 | 1960 | 298742 | operating | 404,5 | | 2 | 175 | 1961 | 298646 | operating | | 3 | 175 | 1962 | 267770 | operating | | 4 | 175 | 1963 | 279784 | operating | | 5 | 175 | 1964 | 276103 | operating | | 6 | 175 | 1965 | 265804 | operating | | 7 | 275 | 1967 | 238445 | operating | | 8 | 300 | 1968 | 237158 | operating | | 9 | 275 | 1969 | 228693 | operating | | 10 | 275 | 1969 | 243818 | operating | Vuglegirska TPP Installed capacity 3600 MW; Number of power units - 7; Basic designed fuel: For power units with an installed capacity of 300 MW - coal of the ГСШ grade (caloric value 5000 kcal/kg); For power units with an installed capacity of 800MW - gas; The share of consumption of natural gas in the fuel structure in 2007 for power units with an installed capacity of 300 MW 1.98% | № of the power unit | Capacity, MW | Year of putting into operation | Operating time by 01.01.2008,hours | Current state of machinery | Specific reference fuel consumption (2007) g/kW*h | | 1 | 300 | 1972 | 235837 | operating | 367,8 | | 2 | 300 | 1973 | 233023 | operating | | 3 | 300 | 1973 | 229340 | operating | | 4 | 300 | 1973 | 210611 | operating | | 5 | 800 | 1975 | 148343 | operating | | 6 | 800 | 1976 | 127365 | laying-up | | 7 | 800 | 1977 | 133159 | operating |
|